The foundation stampers anonymous is the bottom of a construction which has the function to continu

Work Pile Cap and Tie Beam in New Building stampers anonymous University of Semarang | Community Civil Engineering Student Employee Class USM
Blog Stats Visitors 57.913 Category Posts Select Category 1 (1) Class Information (1) Material stampers anonymous Lecture (8) General (2) Civil Engineering Student Community USM Employee Class Warning BPOM on Plastic Bags Food
To all dear visitors can ask spread to colleagues, relatives or neighbors around you this information useful. Previously we thank you for visiting. Work Pile Cap and Tie Beam in New Building University of Semarang
After the erection process is completed followed by the cutting of piles and pile cap continued to work and Tie beam This work is a preliminary work on the structure above (upper structure) after work under the structure (sub-structure) is completed. All materials used for this work must meet the terms at [...] Employment Development Foundation stampers anonymous Piles New Building University of Semarang
The foundation stampers anonymous is the bottom of a construction which has the function to continue the construction load into the soil layer under the foundation. A foundation design said to be true if the load transmitted by the foundation into the ground does not exceed the power of the land concerned. If the soil strength is exceeded then aka [...] Working Reinforced Concrete Portal using SAP 2000 V.11
Known portal structure of concrete f'c = 20 MPa working dead load (DL), live load (LL), and seismic load (EL) as shown, beam dimensions 35 x 50 cm2, and column 30 x 30 cm2, Resolution: a. Determining the Structure Model 1) Set the unit to kN.mC unti 2) Select the File menu - New Model, the [...] Calculating examples Steel Bridge Structures with SAP 2000 V.11
Known Seatu steel truss bridge with the following data: Landscape 6 x 6.0 m, height 5.0 m Profile used IWF 14 x 90 Fy = 240 MPa Expenses that work is Dead load (DL) and load Life (LL), where the weight of its own structure is included in the loading DL = [...] CALCULATION OF FOUNDATION
Soil Data Analysis and Research Foundation is a structure under which serves to put the building on the ground and pass on the burden to the base. For that should be carried out investigation of soil conditions at the site will be built. From the results of Test Boring (Boring Logs) Depth 0.00 ms / d -0.20 m in the form of stone and gravel urugan ground. Depth [...] Comparison stampers anonymous of Concrete Compressive Strength
In the design of reinforced concrete structural components, concrete compressive load is assumed to just accept it. Thus, the quality of concrete is always associated with its ability to carry the load tap (or the term compressive strength). Determination of compressive strength of concrete can be obtained through laboratory testing in the press. The test specimen is used usually are: Specimens [...] unit price indices foundation work
6.1 Installing 1 m3 foundation stone sides, stampers anonymous mix 1 PC: 3 PP 6.2 Installing 1 m3 foundation stone sides, mix 1 PC: 4 PP 6.3 Installing 1 m3 foundation stone sides, mix 1 PC: 5 PP 1 m3 6.4 Installing the foundation stone sides, mix 1 PC: 6 PP 6.5 Installing 1 [...] Output styles - in the SAP Program 2000
Style - the style in which results from the analysis of the structure of the SAP program in 2000 include: 1) Style Normal / axial (P) 2) shear force / latitude in the field 1-2 / shear (V2) 3) Style shear / latitude on field 1 -3 / shear (V3) 4) The torque / torsion (T) 5) moment on the field 1-3 [...] MPA Students Evening Class of 2009
On February 20, 2009 Students of Civil Engineering MPA to hold evening classes Gajah Mungkur Winton Before Departing receive direction from the Chairman of the Department of Civil Engineering, namely Bp. Purwanto, ST, MT setekah get briefed on Kajur Civil Engineering approximately 15 minutes, directly to the left bus slid into Winton, until in solo at 9 p [...] Administrator Register Log in Entries RSS Comments RSS WordPress.com
After the erection process is completed followed by the cutting of piles and pile cap continued to work and Tie beam This work is a preliminary work on the structure above (upper structure) after work under the structure (sub-structure) is completed. All materials used for this work must comply with the applicable regulations. The work pile cap and tie beam includes:
Reinforcement is a work that aims to establish and install reinforcement of concrete stampers anonymous as a structural framework in concrete construction to conform to the plans. stampers anonymous Functions in concrete reinforcement is to resist compressive force, shear and torsional moments arising from the load acting on the concrete construction. In accordance with the concrete nature of the strong against the press, te